WALL FORMWORK SYSTEM

Home  >  TRANSKON Wall Formwork System > Erection Procedure

Erection Procedure
      

Before supplying Transkon equipment our Technical Department will design the equipment required to construct the project. Drawing and quantity lists will be supplied detailing the layout of the panels.

FOR CRANE HANDLED GANGFORM SYSTEM
  1. The panels are laid out on a flat surface and joined will wedge sets.

  2. Tubes and/or channels are attached to the panels with "B" clamps or "C" clamps.

  3. The assembled gangform is lifted into position either manually or with a crane.

  4. Ties are inserted through the tie holes, the plastic tube having been cut to the correct length in accordance with the width of the concrete wall to be poured.

  5. Push-pull props are secured to the ground and to the gangform and are adjusted to achieve accurate vertical plumbing.
      


Steel faced economy panels and single channel aligning walers with ties through the panel.


 

Typical wall plan showing a panel layout of economy panels and internal corner panels using aligning channels with ties through the panel onto twin channel soldiers.

 


 