ERECTION PROCEDURE

Home  >  UNISPAN Erection Procedure

The scaffold should be erected in continuous sequence starting from the corner of the structure or the highest ground level point. The ground must be compacted first.

Four base jacks are adjusted to the same height.

A standard is placed onto each of the first two adjustable jacks. While one person holds the two standards, the other person fits the required ledger to the standards.
   
   
          

Hold standards upright to allow additional ledgers to be fitted first at 90° to the standard. Connect next row of standards and jacks to complete the first row which must be properly aligned, plumbed and squared.

Additional bays can now be added by means of standards and ledgers.
   
   
    

 